Case Study – Billericay Station Platform One Lift Renewal

Client: Greater Anglia Value: £800k Duration on site: 22 Weeks Capel CS tendered and were awarded a lift renewal scheme at Billericay station by train operator Greater Anglia. The scope of the works encompassed the design, removal of the existing passenger lift, supply and installation of a new Network Rail standard hydraulic passenger/goods lift within […]

Case Study – Chelmsford Station Lifts Renewal

Client: Greater Anglia Value: £1,150,000 Duration on site: 41 Weeks Capel CS tendered and were awarded the lifts renewal scheme at Chelmsford station by train operator Greater Anglia. The scope of the works encompassed the design, removal of both existing passenger lifts, installation of two accessible Lift Motor Rooms, supply and installation of two new […]

Pre-Construction Photos

Client: Greater Anglia Value: £175,000 Duration on site: 7 Weeks Capel CS Ltd were requested to complete a survey at Ipswich Station to the roof over the Ticket Office, following ongoing water ingress issues, the survey was completed in collaboration with Greater Anglia to define the scope of works. From the survey results Capel CS […]

Case Study – Colchester Station Car Park Demolition

Client: Greater Anglia Value: £600,000 Duration on site: 20 Weeks Capel CS Ltd were awarded the Contract by Transport UK East Anglia (Greater Anglia Rail) on 30th August 2024 to act as the Principal Contractor to undertake the demolition of the elevated car park deck at Colchester Rail Station. The existing 1200m2 deck car park, […]

Case Study – Bishops Stortford Toilet Refurbishment Works

Client: Greater Anglia Value: £69,500 Duration on site: 6 Weeks In November 2024, Capel CS Ltd were awarded the Male Staff toilet refurbishment at Bishops Stortford Station for Greater Anglia. The employer’s brief was for the existing sanitary ware to be replaced, toilet pans would be replaced with Anti-Ligature pans and concealed cisterns, the number […]